Scottish Water SR27 (2027 to 2033) for Equipment Suppliers

Scotland is not in AMP8. How Scottish Water buys equipment for SR27: the £7.9bn final determination, the Enterprise partners who must use its frameworks, the equipment frameworks on its forward plan and how to bid.

TC

The ChemCapital Editorial Team

Procurement Intelligence ·

Share
Photograph of a modern water treatment works with steel buildings and round tanks on the shore of a Scottish loch below misty mountains, with a navy blueprint panel showing three steps: register on the portal, win a framework place, supply the partners
In Scotland the Enterprise partners must use Scottish Water's own supply chain frameworks, so those frameworks are where equipment makers win SR27 work. Image credit: ChemCapital

Scotland is not part of AMP8. Scottish Water's next investment period, SR27, runs from 1 April 2027 to 31 March 2033, and its regulator, the Water Industry Commission for Scotland, published its final determination on 12 November 2026 supporting £7.9bn of investment [1], 30% more than the current period [2]. For an equipment maker the key fact is this: Scottish Water's delivery partners must use Scottish Water's own supply chain and specialist frameworks [3], and its forward plan lists framework procurements for pumps, valves, dosing equipment, blowers, instrumentation and motor control centres [4]. Those frameworks, tendered on Scottish Water's Atamis portal [5], are the way in.

ChemCapital is not affiliated with Scottish Water. Tendering happens only through Scottish Water's own portal, described below, and its supplier page mentions no fee. Checked on 24 November 2026.

Scotland runs on a different cycle and different rules

Most supplier guides treat the UK water industry as one market. For a supplier, Scotland differs in almost every practical respect:

England and WalesScotland
Current investment periodAMP8, April 2025 to March 2030SR21 until March 2027; then SR27, April 2027 to March 2033 [2]
Economic regulatorOfwatWater Industry Commission for Scotland [1]
Procurement rulesProcurement Act 2023Utilities Contracts (Scotland) Regulations 2016 [5]
Where tenders runEach company's own portal, notices on Find a TenderScottish Water's Atamis tender portal [5]

The final determination caps annual increases in charges at 2.5% above inflation [1]. Scottish Water has until 11 January 2027 to decide whether to accept it [2], so treat the £7.9bn as the regulator's figure until then.

Scottish Water frameworks are tendered one category at a time. List your products free on ChemCapital so other buyers can find you by duty, size, material and certification and invite you to quote in the meantime.

The Enterprise delivers a third of SR27, and must use Scottish Water's frameworks

Scottish Water's largest ever procurement, Delivery Vehicle 4, created the Enterprise: seven partners working with embedded Scottish Water staff against shared outcomes [6] [3]. Scottish Water expects it to deliver a third of SR27 investment [6].

RolePartnersContract value each
Primary DesignersAECOM, Stantec£650m
Asset Delivery Partners (design and build across civils, infrastructure and MEICA)M Group Water, Mott MacDonald Bentley, Farrans, WGM Engineering, Ross Shire Engineering£1.54bn

Values as reported from the award notice in March 2026 [7]. The term runs to March 2033 with an option of six more years to March 2039 [3].

The sentence that matters most to an equipment maker is in the original notice: successful bidders "will be required to utilise Scottish Waters Supply Chain and Specialist Frameworks" [3]. The same notice says Scottish Water plans, for SR27, a Domestic Subcontract Network and a regional framework for smaller and specialist firms, wider frameworks for materials, plant and specialist water and wastewater equipment, and a review in 2030 that may bring in more partners [3]. In England a maker usually has to win over each contractor; in Scotland the place to win is Scottish Water's own frameworks.

How equipment reaches Scottish Water in SR27: Scottish Water awards equipment frameworks on its Atamis portal, the Enterprise partners are required to use those frameworks, and smaller firms have a planned subcontract network and regional framework

The equipment frameworks on Scottish Water's forward plan

Scottish Water spends about £1.4bn a year with 440 supply chain partners across 184 frameworks; about 70% of its framework suppliers are SMEs and 90% of supply chain spend goes through businesses based in Scotland [4]. Its 2024/25 report lists the procurements it planned to start, with target dates but no values [4]:

ProcurementTarget start
Pressure reducing valvesJune 2025
CSO screens; screens and screenings handlingAugust 2025
Trickling filters; static mixers; wash down booster sets; modular pumping stationsNovember 2025
Remote telemetry unitsDecember 2025
Valves and penstocksFebruary 2026
Wastewater packaged plantJuly 2026
Chemical dosing equipment; the supply of pumps; blowers and compressors; instrumentation; motor control centres and systems integration; bridge scrapers; filtration mediaAugust 2026
Portable and fixed gas detectionMay 2027

These are targets set in 2025, and some will have moved. Check the tender portal for each category that fits your range, and if a target date has passed without a tender, ask Scottish Water's procurement team whether it is still planned. Frameworks it awarded in 2024/25 show the range it buys directly: low carbon and GRP kiosks, water sampling kiosks, laboratory equipment, glass fused steel tanks and cartridge filters among them [4]. Our guide to framework agreements for pumps, valves and instruments explains how these arrangements are run.

How to bid

  1. Register on the Scottish Water Tender Portal. Scottish Water runs the whole process there, from advertisement and prequalification to tender and award [5].
  2. Prepare to sign the Supplier Code of Conduct. All framework suppliers and contractors must [5].
  3. Plan community benefits. Tenders ask what you will commit to, such as modern apprentices, graduates, jobs for long term unemployed people or work with supported businesses, and the commitments are written into contracts and monitored [4].
  4. Show how you will support Scottish sites. Nothing requires a Scottish base, but 90% of supply chain spend goes through Scotland based businesses [4], so set out how you will support Scottish sites, for example through a named service partner or engineer in Scotland.
  5. Answer the prequalification well. Our guide to supplier qualification questionnaires covers the standard sections.

Scottish Water's standard terms are 30 days from receipt of an undisputed invoice, it reported paying 96% of invoices within 30 days, and its contractors must pay their subcontractors within 30 days [4].

Practical example

All figures are illustrative. A pump maker based in the north of England sees "The supply of pumps" on Scottish Water's forward plan. It registers on the tender portal, sets an alert for the category, and prepares a prequalification response with its ISO certificates, reference sites and a service partner in Central Scotland. For community benefits it commits to one modern apprentice over the life of the framework and to work experience placements at its service partner.

When it wins a place and an Enterprise partner calls off a £120,000 order through the framework, the maker's terms on the framework apply. If Scottish Water itself buys spares, its 30 day terms mean the maker is paid a month sooner than under the 60 day terms some English water companies use, worth about £790 on £120,000 at an 8% cost of borrowing.

Being found beyond one framework

A framework place makes you the supplier Scottish Water's partners must use for that category. Buyers outside it, in Scotland and elsewhere, still have to find you. ChemCapital lists suppliers by what they make: buyers search by duty, size, material and certification and can invite you to quote before you are on their approved vendor list. You can see what a free supplier listing includes.

Ready to be found while the SR27 frameworks are tendered? List your company on ChemCapital. It is free to start.

Frequently asked questions

What is Scottish Water SR27?

SR27 is Scottish Water's regulatory and investment period from 1 April 2027 to 31 March 2033. The Water Industry Commission for Scotland's final determination of 12 November 2026 supports £7.9bn of investment, 30% more than the current period. Scotland is not part of AMP8.

How do I become a Scottish Water supplier?

Scottish Water tenders under the Utilities Contracts (Scotland) Regulations 2016 and runs the whole process on its Atamis tender portal, where you register and see current tenders. Framework suppliers must sign its Supplier Code of Conduct.

Who are the Scottish Water Enterprise partners?

AECOM and Stantec as Primary Designers, and M Group Water, Mott MacDonald Bentley, Farrans, WGM Engineering and Ross Shire Engineering as Asset Delivery Partners. The Enterprise is expected to deliver a third of SR27 investment and must use Scottish Water's supply chain and specialist frameworks.

What are Scottish Water's payment terms?

Its 2024/25 procurement report gives standard terms of 30 days from receipt of an undisputed invoice and says 96% of invoices were paid within 30 days. Its contractors must pay subcontractors within 30 days.

Informational only, not procurement or legal advice. Cited names, frameworks, and statistics belong to their respective owners.

Share this article

Send it to a colleague or stakeholder.

Be found by buyers who search by specification

Create your profile and list your products so buyers can find you and invite you to quote. It is free to start: list up to five products and quote on your first three RFQs at no cost.

List your products free

Related articles