Approved Supplier for Sterile and Biologics Sites: The Document Pack by Equipment Type
What a sterile or biologics site asks an equipment supplier for, by equipment type: vessels, valves, pumps, filter housings, skids, isolators and single use assemblies, traced to EU GMP Annex 1 and Annex 15, ASME BPE and GAMP 5.

A sterile or biologics site approves an equipment supplier on the evidence that comes with the equipment: certificates for every product contact material, weld and surface finish records, a written design description, test protocols the site can reuse, and the instructions it needs for cleaning, sterilisation and maintenance. No regulator approves the equipment for you. The US FDA says it keeps no list of approved equipment [1], and EU GMP puts the job on the site, which must check your design against its user requirements and verify your materials of construction when it installs your equipment [2]. The table below sets out the pack by equipment type.
ChemCapital is not affiliated with the European Commission, PIC/S, ASME, ISPE or the FDA. This guide summarises their published texts; the buyer's own specification decides what you must supply. Checked on 24 November 2026.
The site carries the approval, so it asks you for the evidence
Under EU GMP Annex 15, qualification starts with the site's user requirements specification, which stays the point of reference for the whole life of the equipment. Design qualification then checks your design against it, and installation qualification includes verifying materials of construction, collecting your operating and maintenance instructions and calibrating instruments [2]. In the US, the rule is that product contact surfaces must not be reactive, additive or absorptive in a way that alters the product [1]. Every document a sterile site asks you for traces back to one of those checks.
Annex 1, the EU rules for sterile manufacture in force since 25 August 2023, adds the sterile layer. It expects a written, detailed description of each equipment design, with P&IDs where appropriate, cleaning that is validated, and sterilisation of the direct and indirect product contact parts used in aseptic processes [3]. Our Annex 1 guide for equipment buyers covers how that changes the RFQ.
Sterile and biologics sites approve suppliers whose evidence they can check. List your products free on ChemCapital so their engineers can find you by duty, size, material and certification and invite you to quote.
The document pack by equipment type
| Equipment | Documents to have ready | Where the request comes from |
|---|---|---|
| Vessel or tank | Material test reports for product contact metal; weld log and examination records; surface finish readings; passivation record; drawings and P&ID | ASME BPE documentation, surface finish and passivation parts [4]; Annex 15 materials check [2]; Annex 1 design description [3] |
| Diaphragm valve | Material test report for the body; certificate of conformance for the diaphragm and seals; surface finish; suitability for the site's sterilisation method | ASME BPE certificate of conformance for polymeric parts [4]; Annex 1 sterilisation of contact parts [3] |
| Hygienic pump | Certificates for wetted metal and elastomers; cleaning and sterilisation limits; operating and maintenance instructions | US surface rule [1]; Annex 1 cleaning validation [3]; Annex 15 supplier instructions [2] |
| Filter housing | Material and finish records for the housing; for the elements, the filter maker's data on extractables and integrity testing | Annex 1 filter leaching and integrity testing [3] |
| Process skid | Design description and P&ID; FAT protocol and report; software documents; calibration certificates; vendor IQ and OQ protocols if offered | Annex 1 [3]; Annex 15 FAT and vendor protocols [2]; GAMP 5 [5] |
| Isolator | Glove integrity testing approach; the automated bio decontamination system and its sporicidal agent; qualification data | Annex 1 isolator rules [3] |
| Single use assembly | Certificate of conformance and proof of sterilisation for each unit; extractables data; data on failure modes | Annex 1 single use rules [3] |
For single use systems, Annex 1 is unusually direct about suppliers: assessing the supplier, including sterilisation, is critical, the site checks evidence of sterilisation on receipt, and the supplier assessment should collect data on failure modes that could break sterility [3]. If you make or assemble those systems, expect to be audited on exactly that.
What every pack has in common
ASME BPE, which ASME describes as the leading standard for equipment used to make biopharmaceuticals, covers materials, design, fabrication, inspection, testing and certification [6]. Its 2024 contents include forms for material examination and weld and inspection logs, a table of what a certificate of conformance must contain for polymeric parts, a part on process contact surface finishes, a section on passivation, and vendor documentation requirements for new instruments [4]. Build those records as you fabricate rather than at the end; our guides to passivation and electropolishing and the vendor document requirement list explain the formats buyers expect.

FAT records can save the site repeat tests
Annex 15 lets equipment with novel or complex technology be evaluated at the vendor before delivery, and lets documentation review and some tests done at the factory acceptance test stand without repeating them at installation, if transport and installation do not affect the function [2]. Protocols a vendor supplies can be used once the site confirms they suit its procedures [2]. GAMP 5's second edition, published in July 2022, goes further for automated systems and encourages regulated companies to make the most of supplier knowledge, experience and documentation [5]. A clear FAT protocol for a process skid is therefore worth money to the buyer, and it is a reason to choose you.
Check which edition the specification names
ASME issued the 2024 edition of BPE on 29 April 2024 and scheduled the next edition for 2026 [4]. A specification written against one edition may differ in detail from the next, so confirm the edition before you quote. Annex 15 is also under review: EMA and PIC/S consulted on a concept paper to replace it between 9 February and 9 April 2026 [7]. The current text came into operation on 1 October 2015 [2]; check whether a revised version has been published before you rely on its wording.
Practical example
All figures are illustrative. A 12 person UK fabricator wins a £95,000 order for a 1,000 litre jacketed buffer vessel for a biologics site. The specification calls up ASME BPE and asks for a full turnover pack: material test reports for every product contact component, a weld log covering each product contact weld with its examination record, surface finish readings and the passivation record.
Compiling the pack takes 38 hours at £60 an hour, £2,280, or 2.4% of the order value. Because the fabricator built the weld log during fabrication, the site's quality team accepts the pack at the FAT and does not repeat the document review at installation, as Annex 15 allows [2]. On its next quote the fabricator prices the document pack as its own line, so the cost is visible and the buyer can see what it is paying for.
Being found by sterile and biologics buyers
A sterile site can only approve what it can check, so suppliers who already produce this evidence are easier to shortlist. ChemCapital lists suppliers by what they make: buyers search by duty, size, material and certification and can invite you to quote before you are on their approved vendor list. You can see what a free supplier listing includes.
Ready to be found by sterile and biologics buyers? List your company on ChemCapital. It is free to start.
Frequently asked questions
Does a regulator approve process equipment for sterile manufacturing?
No. The US FDA says it keeps no list of approved equipment, and EU GMP makes the manufacturing site responsible for qualifying equipment against its own user requirements. The site approves the supplier on the documents that come with the equipment.
What documents does a biologics site ask an equipment supplier for?
Usually material test reports for product contact metal, certificates of conformance for seals and diaphragms, weld logs with examination records, surface finish readings, passivation records, a design description with P&IDs, test protocols and operating and maintenance instructions.
Can factory acceptance tests replace tests on site?
Sometimes. EU GMP Annex 15 allows documentation review and some tests done at the factory acceptance test not to be repeated at installation, if the site can show transport and installation do not affect the function.
Which edition of ASME BPE applies?
The one the buyer's specification names. ASME issued BPE 2024 on 29 April 2024 and scheduled the next edition for 2026, so confirm the edition before quoting.
Continue reading
Informational only, not procurement or legal advice. Cited names, frameworks, and statistics belong to their respective owners.
Be found by buyers who search by specification
Create your profile and list your products so buyers can find you and invite you to quote. It is free to start: list up to five products and quote on your first three RFQs at no cost.
List your products freeRelated articles

Approved Supplier for API and Fine Chemical Plants: What They Ask That Sterile Sites Do Not
API and fine chemical sites ask equipment suppliers for GMP evidence under ICH Q7 and safety evidence for hazardous areas, pressure and containment. What each requirement means for your approval pack, with an illustrative filter dryer example.

Sustainability Requirements for Equipment Suppliers: SBTi, EcoVadis, TfS and PSCI
What pharma and chemical buyers now ask a 50 person equipment fabricator for on sustainability, which requests are firm and which are preferred, and what SBTi validation, EcoVadis, TfS, PSCI and UK Carbon Reduction Plans take.

Shell Supplier Qualification: The Profile Questionnaire and HSSE Assessment
Shell registers suppliers by invitation from its procurement data team. How the invitation, the Supplier Profile Questionnaire, ethics, financial and HSSE checks and the Ariba accounts work, and how to spot fake Shell vendor registrations.