Aramco Vendor Registration for Equipment Manufacturers: The Route and What It Does Not Give You

How an equipment maker outside Saudi Arabia becomes an approved Aramco source: the regional sourcing list, eMarketplace registration, technical and quality approval, 9COM numbers and the RVL.

TC

The ChemCapital Editorial Team

Procurement Intelligence ·

Share
Photograph of a large gas processing plant in a flat desert at golden hour, with tall columns and pipe racks, and a navy blueprint panel showing three steps: register, qualify, 9COM linked
Registration is the first of three gates at Aramco: the plant must be qualified and linked to 9COM numbers before enquiries follow. Image credit: ChemCapital

To become an Aramco supplier as an equipment maker outside Saudi Arabia, you need three things, not one: a supplier record on Aramco's eMarketplace, which runs on SAP Ariba [1], approval of your plant by Aramco's technical and quality teams, and a link between your company and specific 9COM material numbers [2]. None of that starts unless your product appears on the Materials Sourcing List held by your regional Aramco office, and Aramco Europe says plainly that it only begins prequalification for items on that list [3].

ChemCapital is not affiliated with Aramco. Registration with Aramco is free and happens only through Aramco's own channels, described below. Checked on 24 November 2026.

Registered, qualified and approved are three different states at Aramco

Most suppliers treat "registered" as the finish line. At Aramco it is the first of three gates.

Registered means you hold a SAP Ariba account, have completed the supplier questionnaire and have a vendor ID. Aramco Americas spells out that registration does not mean you are qualified to supply materials [4]. Aramco's January 2025 guide says an approved registration produces a Saudi Aramco Vendor ID in the format 100xxxxx [2].

Qualified means your manufacturing plant has passed Aramco's technical and quality review. The same guide describes parallel workflows to the technical and quality teams, run by an account manager, and says Aramco inspectors may visit the plant to check your quality system against ISO 9001 and your ability to meet the material specification [2].

Approved for a material means your company is linked to one or more 9COM numbers. Aramco defines 9COM as its classification for a commodity or class of materials, not a specific item [5]. Only once both the technical and quality teams approve, and you are linked to the selected 9COMs, does Aramco treat you as an approved and qualified source of supply [2].

The difference matters when you plan sales effort. A vendor ID with no 9COM link will not bring enquiries for your product. And approval is product by product: Aramco Asia India notes that extending approval to more materials means completing the full approval process again, and only for materials on the current list [5].

Aramco approval covers one buyer, product by product. List your products free on ChemCapital so other buyers can find you and invite you to quote while it runs.

Your regional office decides whether you can start

Aramco's head office in Dhahran handles suppliers in Saudi Arabia, the Gulf and the wider Middle East and North Africa. Suppliers elsewhere are sent to a regional supplier registration office; the January 2025 guide lists offices for the Netherlands, Japan, Singapore and the Philippines, India, China and the Americas [2]. Each office works from its own sourcing list and its own front door.

Where your factory isWho handles youHow the first step works
Saudi Arabia, the Gulf, wider Middle East and North AfricaHead office, DhahranRegistration request on the eMarketplace [2]
EuropeAramco Europe materials sourcing teamEmail listing the sourcing list items you make; prequalification only for listed items [3]
India and Sri LankaAramco Asia IndiaIts own supplier page; it handles these two countries only [5]
United States and CanadaAramco AmericasRegistration for new suppliers by invitation, per its FAQ last updated January 2019 [4]
China, Japan, Singapore and the PhilippinesRegional offices named in the 2025 guideContact the office for your country [2]
Anywhere elseAramco Supplier HelpdeskAsk which office covers you [5]

Two details in that table save weeks. First, Aramco Europe's current list is dated March 2026, and the page warns that an application for something not on it will not start prequalification [3]. Read the list before you write anything. Second, Aramco Asia India says the list is updated periodically with no fixed schedule, and a product not on it may be added later [5]. If your product is missing, keep checking rather than applying anyway.

You do not need a Saudi representative to register, according to the same FAQ [5].

The route for a manufacturer outside Saudi Arabia has six steps

Putting the official documents together, the route looks like this.

  1. Check the sourcing list of your regional office and note the items you actually make [3].
  2. Apply through your regional office, listing those items. In Europe that is an email to the materials sourcing team [3].
  3. Register on the eMarketplace. Submit the registration request through SAP Ariba. A dedicated analyst reviews the package and, on approval, issues your vendor ID [2].
  4. Send the technical and quality packages. The account manager starts the technical and quality reviews in parallel [2].
  5. Host a plant visit if asked. Inspectors may assess your quality system and your ability to meet Aramco's material specifications; corrective actions are reported to management [2].
  6. Get linked to 9COM numbers. With both approvals and the 9COM link, you are an approved source of supply [2]. After that, you are invited to bid when a requirement arises for your approved item [5].

Six step route for an equipment manufacturer outside Saudi Arabia to become an approved Aramco source: check the regional sourcing list, apply through the regional office, register on the eMarketplace and receive a vendor ID, send technical and quality packages, host a plant visit if asked, and be linked to 9COM material numbers

Aramco also keeps paper registration forms, including the Out of Kingdom Manufacturer Registration Form SA 9676, but its supplier resources page says they are used only when Aramco's registration staff direct it [1]. Do not send a form nobody asked for. If you are asked, the next section is what it takes.

Form SA 9676 asks for three document packages, authenticated

The out of Kingdom manufacturer form is the clearest public statement of what Aramco wants to know about a factory [6]. It runs to fifteen sections, from plant capacity and manpower to welding, NDT, coating and heat treatment processes, approved sub suppliers and past Aramco orders. The supporting documents fall into three packages.

PackageWhat it contains (from form SA 9676)
CommercialSigned Supplier Code of Conduct acknowledgement, a letter of identification on letterhead, commercial registration, industrial licence, bank letter, and ownership documents traced through every indirect owner
QualityQuality manual, the mandatory ISO 9001 procedures, the ISO 9001 certificate, recent management review minutes, the latest surveillance audit report, organisation chart naming QA and QC staff, inspector certifications, QA and QC manager qualifications
TechnicalCompany profile, product catalogue with specifications, production flow chart, key equipment and raw materials, production manager's CV, major users with contacts, sub vendor list with scope, and a compliance letter against Aramco engineering standards

The signing rules catch people out. The form must be signed by an authorised representative, stamped with the company stamp, and authenticated by the chamber of commerce of your country or an equivalent government authority. The Code of Conduct acknowledgement and the letter of identification need the same treatment. One soft copy goes through Aramco's file sharing platform and one physical copy goes to Dhahran [6].

Separately, Aramco Europe says no new procurement proceeds without a signed Supplier Code of Conduct, and the version on its page was updated in October 2026 [3]. Sign the current one, not a copy from an old tender.

Much of the quality package is what any careful buyer asks for. Our guides to preparing for a customer quality audit and to answering a supplier qualification questionnaire cover how to build it once and reuse it.

Most equipment reaches Aramco projects through EPC contractors and the RVL

On a capital project, the purchase order for your pump or vessel usually comes from an engineering contractor, not from Aramco itself. That changes who you need to convince.

Saipem, which executes Aramco projects, told its suppliers in November 2024 that Aramco treats adherence to codes such as ASME and API, plus Aramco specific requirements such as Schedule Q, as non negotiable [7]. The same slides ask vendors to use the sub vendors the RVL requires and to declare any deviation from it, or any change of manufacturing location, at bid stage, because doing it after award causes delay [7]. Aramco's own glossary expands RVL as the regulated vendor list [5].

Two practical consequences follow. If you make a component that goes into other makers' packages, getting onto the RVL is what puts you in front of every contractor at once. And if you supply a package, check your own sub vendors against the RVL before you quote, not after you win. Our guide to EPC contractor vendor registration explains the two lists, contractor and owner, that most projects run on.

Local content weighs heavily too. Saipem's slides report that suppliers inside the Kingdom were about double those outside it in number and value on its Saudi projects, which it attributes to Aramco's contract requirements and the IKTVA programme [7]. Our IKTVA score worked example shows how that score is built.

Practical example

All figures are illustrative. A UK maker of shell and tube heat exchangers wants to supply Aramco projects.

WeekWhat happensWeeks lost and why
0Checks Aramco Europe's March 2026 sourcing list; its product category is listed0
1Emails the materials sourcing team, naming the listed items0
2 to 4Registration request on the eMarketplace; returned once because the ownership chart stops at the parent company2 (indirect owners missing)
5Vendor ID issued0
6 to 10Quality package assembled; the latest surveillance audit report has to be requested from the certification body2 (document not on file)
11 to 14Technical and quality review; compliance letter against Aramco standards rewritten after questions on two exceptions1 (exceptions not explained)
16Plant visit; one finding on calibration records, closed in two weeks0
18Approved and linked to the relevant 9COM numbers0

Eighteen weeks from first email to approval, five of them lost to gaps the maker controlled. Approval brought invitations to bid on that item only. Its first real order came through a contractor that already had it on the RVL for a package, which is the route most makers should plan for.

Two habits would have saved most of the lost weeks. Keep the ownership chart, audit reports and certificates in one current pack, and write the compliance letter as a numbered list of each standard you meet and each exception, with the reason.

Where ChemCapital fits

Aramco approval takes several steps and covers one buyer. While it runs, it pays to be easy to find for everyone else. ChemCapital lets you list your products and say what you can certify, so buyers searching by duty, size, material and certification can find you and invite you to quote, whether or not you are on their approved list yet.

Ready to be found by buyers while your Aramco approval runs? List your company on ChemCapital. It is free to start.

Frequently asked questions

Can a manufacturer outside Saudi Arabia register as an Aramco supplier?

Yes. Suppliers outside Saudi Arabia, the Gulf and the wider Middle East and North Africa go through their regional Aramco office. The process starts only for products on that office's Materials Sourcing List, and ends with your plant approved and linked to specific 9COM material numbers.

Do I need a Saudi agent or representative to register with Aramco?

No. Aramco Asia India's supplier FAQ says a Saudi representative is not required to register. You may still choose a local partner for sales, service or local content reasons.

What is a 9COM number at Aramco?

It is Aramco's material classification for a commodity or class of materials, not a specific item. A manufacturer becomes an approved source of supply for the 9COM numbers it is linked to after technical and quality approval.

Does Aramco vendor registration guarantee orders?

No. Aramco says registration or prequalification is not a guarantee of future work. Approved suppliers are invited to bid when a requirement arises for their approved items, and many project orders come through EPC contractors buying from the regulated vendor list.

Informational only, not procurement or legal advice. Cited names, frameworks, and statistics belong to their respective owners.

Share this article

Send it to a colleague or stakeholder.

Be found by buyers who search by specification

Create your profile and list your products so buyers can find you and invite you to quote. It is free to start: list up to five products and quote on your first three RFQs at no cost.

List your products free

Related articles