33 articles

Contracts & Post Award

Articles on contracts & post award for industrial procurement teams.

Blueprint style graphic of a reactor on a delivery trailer beside an empty foundation and a calendar, and a card showing about 51,700 pounds a week of delay cost
Contracts & Post AwardFor procurement

Cost of Late Equipment Delivery: Worked Example

How to calculate the weekly cost of late equipment delivery, compare it with liquidated damages and use it to set a damages rate a supplier can accept.

5 min read
Blueprint style graphic of a skid on a test stand above two dipping cash curves, and a card comparing peak funding of 265,000 and 100,000 pounds
Contracts & Post AwardFor suppliers

Payment Milestones and Supplier Cash Flow: Worked Example

How payment milestones, bonds and retention shape an equipment supplier's cash curve, with a worked example comparing two schedules on a £400,000 order.

7 min read
Photograph of a stainless steel process skid with a vertical column, a shell and tube heat exchanger and two pumps, with a clamp on flowmeter and test cables in the foreground
Contracts & Post AwardFor procurement

Performance Guarantees and Performance Tests for Process Packages

What a process package supplier should guarantee, how the performance test is run, and what happens when the plant falls short, with a worked example of performance liquidated damages.

7 min read
Photograph of a process skid with pumps and a vessel being packed in an open timber export crate, wrapped in grey barrier foil with desiccant bags, under a crane hook in a workshop dispatch bay
Contracts & Post AwardFor procurement

Packing and Shipping Specification for Process Equipment: Seaworthy Crates, ISPM 15 and Marking

What a packing specification for process equipment should say: packing levels, ISPM 15 wood, barrier foil and desiccant, lifting points, shipping marks and documents. With a worked crate example.

7 min read
Photograph of a large crated process skid being lifted by a crane at a container port quayside, with shipping containers and a cargo ship behind
Contracts & Post AwardFor suppliers

Payment Terms and Letters of Credit for Equipment Exporters

How equipment exporters secure payment: advance payments and guarantees, confirmed letters of credit under UCP 600, avoiding discrepant documents, retentions, and UK Export Finance support for bonds and working capital.

7 min read
Blueprint style graphic of a delivery calendar with the original date crossed through and a later date marked, a letter icon sent early on the timeline highlighted in amber
Contracts & Post AwardFor suppliers

Delivery Delay Letter: How Equipment Suppliers Tell a Customer Early and Limit Liquidated Damages

How an equipment supplier should notify a customer of a late delivery: notice clauses, excusable delay, what to put in the letter, a template, and how early notice limits liquidated damages.

6 min read
Photograph of a stainless steel process skid with pumps, a vessel and a control panel on a steel frame in a clean assembly workshop, ready for factory acceptance testing
Contracts & Post AwardFor suppliers

CE Marking a Process Skid: The Technical File, Step by Step

What goes in the technical file to CE mark a process skid under the Machinery Directive, how to build it for an assembly of machinery, and what changes when the Machinery Regulation applies from January 2027.

7 min read
Blueprint style graphic of a bound data book with tabbed sections for material certificates, weld map, NDT, pressure test and declarations beside a vessel outline, with a payment release stamp highlighted in amber
Contracts & Post AwardFor suppliers

Manufacturer's Data Book for Vessels and Skids: Compile It So You Get Paid

The final payment on many equipment orders waits for the data book. Here is what it contains, how to build it during fabrication, and how to get it accepted first time.

7 min read
Blueprint style graphic of three identical pump symbols tagged P101A, P101B and P101C linked to one shared mechanical seal part on a spares record, with the shared part highlighted in amber
Contracts & Post AwardFor procurement

SPIR Form: The Spare Parts Interchangeability Record Explained

The SPIR is the supplier's list of every spare part for the equipment you bought, tag by tag, with interchangeability, prices and lead times. Here is how to use it.

5 min read
Blueprint style graphic: on the left a skid with a pump and a vertical vessel, labelled machinery and pressure, joined by one line into an EU declaration of conformity page with seven numbered lines and a signature box highlighted in amber
Contracts & Post AwardFor suppliers

EU Declaration of Conformity for Machinery and Pressure Equipment: Contents and Template

What an EU declaration of conformity must contain under the Machinery Directive, the Machinery Regulation and the PED, who signs it, how long to keep it, and a template for a process skid.

8 min read
Blueprint style graphic: a meeting table outline seen from above with buyer and supplier sides, an agenda card listing scope, data, documents, ITP, schedule and change, and a calendar marker with delivery start highlighted in amber
Contracts & Post AwardFor procurement

Equipment Order Kick Off Meeting: Agenda and Checklist

An agenda and checklist for the post order kick off meeting on engineered equipment: scope, data, documents, ITP and hold points, schedule, change control and payment.

5 min read
Blueprint style graphic: two timelines starting at delivery, one with start up soon after and a full 12 month warranty bar, one with a delayed start up where an amber 18 month long stop cuts the warranty bar short
Contracts & Post AwardFor procurement

Equipment Warranty Terms: 12 Months From Start Up or 18 From Delivery

How engineered equipment warranties are structured, what counts as start, warranty on repaired parts, exclusions, process guarantees, and what UK law adds when the contract is silent.

7 min read
Painted carbon steel pressure vessel on supports in a fabrication shop, set up for a pressure test with a dial gauge and hose on a nozzle, beside a table with a clipboard and torch
Contracts & Post AwardFor procurement

Third Party Inspection for Process Equipment: When to Use It and How to Scope It

What a third party inspector does at your supplier's works, how it differs from a notified body or code inspector, how to pick an accredited agency, and how to scope and price the assignment.

5 min read
Pump skid and small heat exchanger wrapped in grey protective film on timber pallets in a clean warehouse, with flange openings covered
Contracts & Post AwardFor everyone

Preservation and Storage of Process Equipment Before Start Up

How to keep pumps, motors, skids and vessels in good condition between delivery and start up: what to put in the order, storage conditions, shaft rotation, insulation checks and a preservation log.

6 min read
Blueprint style graphic: a cleaning skid with two drawn battery limits, at the skid edge and at the tank nozzles, beside three bids shown quoted and levelled: once missing scope is priced, bid B moves from cheapest to dearest
Contracts & Post AwardFor everyone

Battery Limits, Terminal Points and Scope of Supply in Equipment Quotes

What battery limits, terminal points and scope of supply mean, how gaps between them make quotes look cheaper than they are, and a terminal point schedule you can put in every RFQ.

7 min read
Blueprint style graphic: cumulative delay damages on an 850,000 pound order against weeks late: half a percent a week capped at 7.5 percent, one percent a week capped at 10 percent, and the buyer's standby cost rising above both
Contracts & Post AwardFor everyone

Liquidated Damages for Late Equipment Delivery: Rates, Caps and a Worked Example

How liquidated damages for late delivery work in equipment contracts: how UK courts treat them, how to set the rate and cap, what the clause must say, and a worked example with Orgalim terms.

7 min read
Printed contract pages and a fountain pen on a desk in a plant office, with a process plant blurred through the window
Contracts & Post AwardFor procurement

Purchase Order Terms for Capital Equipment, Clause by Clause

The clauses that decide who pays when equipment is late, fails a test or breaks in year two, with what to check and where suppliers usually push back.

6 min read
Hands holding a handheld analyser against a stainless steel flange in a fabrication workshop
Contracts & Post AwardFor everyone

PMI Testing: When to Require It on a Purchase Order

What positive material identification can and cannot detect, when to require it, how much to test, and how to write PMI into a purchase order and inspection plan.

5 min read
Engineers seen from behind reviewing a marked up drawing beside a partly built process skid in a workshop
Contracts & Post AwardFor everyone

Change Orders and Variations on Equipment Orders

How changes happen on engineered equipment orders after award, how to request, price and approve them, and how buyers and suppliers both stay protected.

5 min read
A process plant under construction at dusk, with cranes and pipe racks against the sky
Contracts & Post AwardFor everyone

EPC vs EPCM: Who Buys the Equipment?

How EPC and EPCM contracts differ, who places equipment orders under each, where cost and schedule risk sit, and what it means for owners, suppliers and long lead items.

5 min read
Thick ring binders of a vendor data book and a stack of engineering drawings on a table in a project office
Contracts & Post AwardFor everyone

Vendor Document Requirement List (VDRL): What to Ask For and When

What a vendor document requirement list is, which documents to ask for at each stage from bid to data book, review codes, and how to put it in the RFQ so it gets priced.

5 min read
A stainless steel process skid with two pumps, a vertical tank, valves and instruments, installed on a concrete plinth in a plant building and connected to overhead pipework, with its control panel beside it
Contracts & Post AwardFor procurement

Site Acceptance Test (SAT) Checklist for Process Skids

What a site acceptance test must prove once a skid is installed, how SAT differs from FAT and commissioning, a full SAT checklist and how to handle failed tests.

7 min read
A spare centrifugal pump rotating assembly on a timber cradle on a steel pallet rack in an industrial spare parts store, with boxed parts and wrapped gaskets on the shelves above
Contracts & Post AwardFor procurement

Recommended Spares List: Commissioning, Operating and Insurance Spares

What a recommended spares list should hold: commissioning, two year operating and insurance spares, criticality, what to ask in the RFQ, and a pump and vessel template.

8 min read
A stainless steel CIP skid with tanks, a pump, a plate heat exchanger and a valve manifold on a painted steel base frame in a plant room, with blank inspection tags tied to a valve and a flange
Contracts & Post AwardFor procurement

Punch List Categories and Mechanical Completion for Process Plant

What a punch list is, how category A, B and C items gate mechanical completion, start up and handover, who clears them, and a template for vendor equipment packages.

8 min read
A stainless steel process skid with pumps, a small vessel, valves and pipework on a painted steel base frame in a fabrication shop, ready for dispatch
Contracts & Post AwardFor procurement

Payment Milestones, Retention and Bonds on Process Equipment Orders

How to tie payment milestones to evidence on process equipment orders, when to hold retention, and what advance payment guarantees, bonds and PCGs secure.

7 min read
Phased array ultrasonic scanner clamped beside a circumferential butt weld on a stainless steel vessel shell in a fabrication bay
Contracts & Post AwardFor everyone

NDT Methods Compared: RT, UT, MT, PT and What to Specify

Compare VT, PT, MT, RT and UT for welded process equipment: what each finds, where each fails, radiography on site, and how to specify NDT extent in an RFQ.

7 min read
A horizontal stainless steel pressure vessel on saddles in a fabrication shop, a pump skid behind it and an inspection folder with a handheld alloy analyser on a workbench
Contracts & Post AwardFor procurement

Inspection and Test Plan (ITP) Template for Pressure Vessels and Skids

What an inspection and test plan is, who writes and approves it, its columns, a complete ITP for a pressure vessel, a short one for a pump skid, and how it ties to payment.

8 min read
A large wooden crate holding a stainless steel process skid, chained to a flatbed trailer at a fabrication works loading bay under an overhead crane hook
Contracts & Post AwardFor procurement

Incoterms for Process Equipment: EXW, FCA, DAP and DDP into the UK

Which Incoterms rule suits a skid or vessel shipped into the UK: who loads, who clears customs, where risk passes and who pays import VAT, with a levelled quote example.

7 min read
Horizontal stainless steel pressure vessel on steel saddles in a fabrication shop, connected to a pressure gauge and test hose for a hydrostatic test
Contracts & Post AwardFor everyone

Hydrostatic Test Pressure: How Each Code Sets It, with Examples

Hydrostatic test pressure is a code multiple of design pressure, corrected for temperature. How ASME VIII, EN 13445, PD 5500 and B31.3 set it, with a worked example.

7 min read
A jacketed stainless steel process vessel nearing completion in a fabrication shop, with packing timber and a shipping skid beside it
Contracts & Post AwardFor procurement

Expediting Equipment Orders: Guide and Weekly Report Template

Expediting keeps an equipment order on its delivery date. Desk and field expediting, the evidence for each milestone, red flags, escalation and a weekly report template.

7 min read
A stack of thick stainless steel plates on timber bearers in a metals warehouse, with small stamped marks along one cut edge.
Contracts & Post AwardFor everyone

EN 10204 3.1 vs 3.2: How to Check a Mill Test Certificate

What EN 10204 2.1, 2.2, 3.1 and 3.2 certificates mean, who validates each, when to ask for 3.2, and a line by line check of an illustrative 316L plate certificate.

8 min read
Stainless steel cleaning in place skid on a navy base frame in a fabrication shop, with test hoses connected and the control panel open
Contracts & Post AwardFor everyone

Factory Acceptance Test (FAT) Checklist for Process Skids

A practical factory acceptance test checklist for process skids: what to agree first, what to check, why FATs slip and how FAT and SAT fit together.

6 min read
Vertical stainless steel pressure vessel set up for a hydrostatic test in a fabrication shop, with a test pump and pressure gauge
Contracts & Post AwardFor everyone

Hold Point vs Witness Point: What They Mean in an ITP

A hold point stops work until the buyer releases it in writing; a witness point lets work go on if nobody comes. ITP codes, notice and costs, with an example.

6 min read